If you are the milestone
verifier, you can search for the milestone
tracker (MT) to enter the verification details. Use Explore Search
on the Home page to locate milestone trackers.
|
|
If your contract is for a construction project, you might use milestones
similar to these to ensure that a certain percentage of the total contract
amount is paid only upon successful completion of each milestone:
Milestone
# |
Pay %
|
Completion Date / Deliverables |
1. Site development,
excavation, foundation work |
20% |
Due January 25, 2004:
Clear vegetation, grade driveway bed, stake out home position,
hook up temporary electricity, dig foundation, pour concrete foundation,
install pipe work, pour concrete floors, dig utility line trenches,
waterproof basement walls, finish rough grading.
|
2. Framing, roofing, exterior work |
20% |
Due February 18, 2004:
Install steel beams, wood frame, windows, exterior doors. Finish
roof, siding, outdoor deck, drainage gutters, garage door. |
3. Mechanical |
15% |
Due April 3, 2004:
Finish plumbing, electrical, heating / cooling, telephone / cable
TV wiring. |
4. Interior finish work & trim |
30% |
Due May 25, 2004:
Interior - Finish insulation, drywall, painting / staining, cabinetry,
countertops, hard floor coverings, baseboards and built-in appliances.
Trim - Finish interior doors, window trims, fireplaces / mantles,
plumbing fixtures, light switches / electrical outlets and fixtures,
heating/cooling units, heating registers, thermostats, central
vacuum face plates, intercom, telephone / cable TV outlets.
|
5. Completion |
15% |
Due June 29, 2004:
Install carpeting, cleanup (exterior and interior), finish driveway,
landscaping, miscellaneous repairs. |
When creating the contract, you designate a verifier to confirm that
each milestone is successfully complete. Once the verifier confirms
completion, the supplier is paid.
|