Ariba Online Help
Contents | Index | Search     
Tips   Milestone statuses

Ariba Buyer emails notification messages to keep relevant users informed of the status of requests, and logs the history onto the History tab.

When adding a milestone to a contract or requisition, the requester can specify that the verifier should receive an email reminder of the impending milestone due date. The verifier is responsible for updating the milestone tracker (MT) with completion details.

Related topics

About contract milestones

About requisition milestones

About notification messages

Notification 79: Milestone Fully Verified

Notification 80: Milestone Verification Required

Notification 81: Milestone Verified

 

To view the status of a milestone, do one of the following:

  • Contracts: display the contract details, and then click the Milestones tab.
  • Requisitions: display the requisition details, and then click the Receipts tab.
This status Indicates
Pending

The milestone tracker (MT) has been created, but has not been verified.

Overdue

The milestone completion due date has passed but the milestone has not been verified.

Verified Incomplete The verifier has indicated that the milestone was not successfully completed.
Verified Complete

The verifier has indicated that the milestone was successfully completed.


Copyright 1996 - 2004 Ariba, Inc. Legal notices.